The Minister of Power, Joseph Tegbe, says reliable electricity supply is essential to achieving President Bola Tinubu’s $1tn economy target, as the Federal Government plans to expand generation and transmission capacity.
Tegbe disclosed this on Friday during an inspection of the ongoing construction of the 480MW New Abeokuta substation at Toolu community, Abeokuta, which is scheduled for inauguration in March 2027, following a cold inauguration in December 2026.
He said industrialization and economic growth could not be sustained without adequate power infrastructure, adding that the government was investing in the sector to support industrial and commercial activities.
The minister said Nigeria was targeting 10,000MW of electricity generation by 2031 and transmission capacity of at least 19,000MW to accommodate increased generation and integrate surplus electricity from renewable energy sources.
He expressed satisfaction with the progress of the Abeokuta project, noting that available equipment and materials would support the completion of installation ahead of its scheduled commissioning.
Also Read: FG begins work on modernization of Lagos ports
Tegbe said the substation was one of five projects under Phase One, Batch One of the Presidential Power Initiative, alongside facilities in Ayede, Sokoto, Offa and Onitsha.
According to him, the five projects are expected to add approximately 986MW to Nigeria’s transmission and wheeling capacity.
He stressed that increasing electricity generation alone would not be sufficient without adequate transmission and distribution infrastructure to deliver power to consumers.
Earlier, the Managing Director and Chief Executive Officer of FGN Power Company, Kenny Anuwe, described the New Abeokuta substation as the flagship project under the first batch of the initiative.
Anuwe said the project involved upgrading an existing 132/33kV facility to a 330/132/33kV substation within an 18-month implementation period.
He said the upgraded facility would provide an additional 480MW of transmission capacity, improve electricity evacuation and strengthen supply reliability, particularly across Ogun State’s industrial corridor.
Anuwe added that the improvements would ease pressure on other parts of the transmission network, including Ikeja West, creating additional capacity to serve the Lagos electricity corridor.